[ovirt-users] [QE][ACTION REQUIRED] oVirt 3.6.0 status

Sandro Bonazzola sbonazzo at redhat.com
Wed Dec 3 04:37:19 EST 2014


Hi,

Release criteria discussion has been closed with last week oVirt sync meeting [1].

Release management for 3.6.0 [2] will soon be updated with the accepted changes in release criteria.
The remaining key milestones for this release must now be scheduled.

For reference, external project schedules we're tracking are:
    Fedora 21: 2014-12-09
    Fedora 22: 2015-XX-XX
    GlusterFS 3.7: 2015-04-29
    OpenStack Kilo: 2015-04-30


Two different proposals have been made about above scheduling [3]:
1) extend the cycle to 10 months for allowing to include a large feature set
2) reduce the cycle to less than 6 months and split features over 3.6 and 3.7

Feature proposed for 3.6.0 must now be collected in the 3.6 Google doc [4]
and reviewed by maintainers.

The tracker bug for 3.6.0 [5] currently shows no blockers.

There are 453 bugs [6] targeted to 3.6.0.
Excluding node and documentation bugs we have 430 bugs [7] targeted to 3.6.0.


[1] http://resources.ovirt.org/meetings/ovirt/2014/ovirt.2014-11-26-15.07.log.html
[2] http://www.ovirt.org/OVirt_3.6_Release_Management
[3] http://lists.ovirt.org/pipermail/users/2014-November/028875.html
[4] http://goo.gl/9X3G49
[5] https://bugzilla.redhat.com/show_bug.cgi?id=1155425
[6] http://goo.gl/zwkF3r
[7] http://goo.gl/ZbUiMc


-- 
Sandro Bonazzola