Hello Milan.
We do not necessary need it earlier, but we want to have some date in mind, so we can plan our CI work accordingly.
Any thoughts for engine? Should it also target Feb 18?
On Feb 19th we should release oVirt 4.3.1 RC (4.3.1 GA na Feb 26th along with RHV 4.3 beta 2), so I'd say let's branch after the final 4.3.1 build ...
Anton.
> On 4 Feb 2019, at 15:41, Milan Zamazal <mzamazal@redhat.com> wrote:
>
> Anton Marchukov <amarchuk@redhat.com> writes:
>
>> Since oVirt 4.3.0 released are we ready to branch master into 4.3?
>
> Regarding Vdsm, there is still an ongoing storage work for 4.3 and no
> really strong pressure for branching out 4.3 I'm aware of. For that
> reason, Vdsm developers have agreed that we could create Vdsm ovirt-4.3
> branch on February 18 (and no significantly later than that). If the
> branch is needed earlier for infra or other reasons, we can make it.
> Storage work would have to be backported, but that can be mostly trivial
> if an initial master-merge rush is avoided.
>
> Thanks,
> Milan
--
Anton Marchukov
Team Lead - Release Management - RHV DevOps - Red Hat