Hi all,
As we agreed in last
scrum meeting (Jan 29th), from now on all the sprints will
have deadlines.
Which means the RFC or first patch series needs to be send to mail
list at the begging of the sprint.
Following are the dates I recommend everyone to follow for sprint
3.
02/03 09:00 (UTC-03:00)
- RFC or first patch series
By this date all tasks planned in the
sprint needs to have RFC or patch on mail list.
02/10 09:00 (UTC-03:00) - Next patch version
Address comments made on RFC and moving
to final patch series version.
It only applies to the tasks planned for the sprint.
All other patches are welcome any time - bug fixes, improvements,
etc.
Regards,
Aline Manera