Release process proposal
Ofer Schreiber
oschreib at redhat.com
Sun Feb 19 14:42:37 UTC 2012
+1 on both comments.
----- Original Message -----
> On 02/19/2012 03:51 PM, Ofer Schreiber wrote:
> > ----- Original Message -----
>
> > > Since we currently doesn't have any official Release process,
> > > here's
> >
>
> > > my proposal:
> >
>
> > > 1. oVirt will issue a new release every 6 months.
> >
>
> > > a. EXCEPTION: First three releases will be issued in a ~3 month
> >
>
> > > interval.
> >
>
> > > b. Exact dates must be set for each release.
> >
>
> > <SNIP>
>
> > Release process proposal V2 (with few open items)
>
> > 1. oVirt will issue a new release every 6 months.
>
> > a. EXCEPTION: First three releases will be issued in a ~3 month
> > interval.
>
> > b. Exact dates must be set for each release.
>
> > 2. A week after the n-1 release is out, a release criteria for the
> > new release should be discussed.
>
> > a. Release criteria will include MUST items and SHOULD items (held
> > in
> > wiki)
>
> > + MUST items will DELAY the release in any case.
>
> > + SHOULD items will include less critical flows and new features.
>
> > + SHOULD items will be handled as "best-effort" by component owners
>
> > b. Component owners (e.g. Node, engine-core, vdsm) must ACK the
> > criteria suggested.
>
> > c. Release criteria discussions shouldn't take more then 2 weeks
>
> > d. Progress on MUST items should be review every month, during the
> > weekly meeting
>
> > 3. Discuses the new version number according to the release
> > criteria/amount of features.
>
> > a. Versions will be handled by each component.
>
> > b. The general oVirt version will the engine version.
>
> > 5. 60 Days before release - Feature freeze
>
> > a. EXCEPTION: 30 days for 3 month release cycle
>
> > b. All component owners must create a new versioned branch
>
> > c. "Beta" version should be supplied immediately after.
>
> > + And on a nightly basis afterwards.
>
> > d. Stabilization efforts should start on the new builds.
>
> > e. Cherry-pick fixes for high priority bugs.
>
> > + Zero/Minimal changes to user interface.
>
> > + Inform in advance on any user interface change, and any API
> > change.
>
> > f. At this stage, we should start working on the release notes.
>
> > 6. 30 days before release - release candidate
>
> > a. EXCEPTION: 15 days for 3 month release cycle
>
> > b. If no blockers (MUST violations) are found the last release
> > candidate automatically becomes the final release.
>
> > + Rebuild without the "RC" string.
>
> > + ANOTHER OPTION- Avoid "Beta" or "RC" strings, just use
> > major.minor.micro, and bump the micro every time needed.
>
> > c. Release manager will create a wiki with list of release blockers
>
> > d. Only release blockers should be fixed in this stage.
>
> > e. OPTIONAL: final release requires three +1 from community members
>
> > + This item is currently optional, I'm not sure what a +1 means
> > (does
> > a +1 means "I tested this release", or "This release generally
> > looks
> > fine for me"?)
>
> >
>
> > 7. Create a new RC if needed
>
> > a. There must be at least one week between the last release
> > candidate
> > and the final release
>
> > b. Go/No go meetings will happen once a week in this stage.
>
> > + Increase the amount of meeting according to the release manager
> > decision.
>
> > + Release manager will inform the community on any delay.
>
> > 8. Release
>
> > a. Create ANNOUNCE message few days before actual release.
>
> > b. Move all release candidate sources/binaries into the "stable"
> > directory
>
> > c. Encourage community members to blog / tweet about the release
>
> > d. PARTY
>
> > Have any comments? ideas? share them with the list!
>
> please consider the following:
> -6. f.30 days before release - release candidate - Test day - i think
> should be part of the process
> -6. g.30 days before release - dev leads/representatives from each
> component participation on the weekly meetings statuses Moran.
> > Thanks,
>
> > Ofer Schreiber.
>
> > _______________________________________________
>
> > Arch mailing list Arch at ovirt.org
> > http://lists.ovirt.org/mailman/listinfo/arch
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ovirt.org/pipermail/arch/attachments/20120219/9cb6dee7/attachment.html>
More information about the Arch
mailing list