[Users] oVirt 3.4.0 release schedule updated
Sandro Bonazzola
sbonazzo at redhat.com
Thu Jan 9 14:23:29 UTC 2014
Here is updated schedule.
I've added 3.3.3 too and attached an ICS calendar with the same dates
These are tentative planning dates and may change
oVirt 3.4 General availability: 2014-02-24
oVirt 3.4 Second Test Day: 2014-02-19
oVirt 3.4 RC Build: 2014-02-17
oVirt 3.4 Test Day: 2014-01-23
oVirt 3.4 Beta release: 2014-01-20
oVirt 3.4 Branching / Feature freeze: 2014-01-15
oVirt 3.4 Alpha release: 2014-01-09
more details on test days, etc to come in the next few weeks
oVirt 3.3.3 General availability: 2014-01-28
oVirt 3.3.3 RC Build: 2014-01-21
oVirt 3.3.3 Beta release: 2014-01-13
Il 09/01/2014 15:02, Doron Fediuck ha scritto:
>
>
> ----- Original Message -----
>> From: "Eli Mesika" <emesika at redhat.com>
>> To: "Sandro Bonazzola" <sbonazzo at redhat.com>
>> Cc: "arch" <arch at ovirt.org>, "engine-devel" <engine-devel at ovirt.org>, "vdsm-devel" <vdsm-devel at fedorahosted.org>,
>> "VDSM Project Development" <vdsm-devel at lists.fedorahosted.org>, Users at ovirt.org
>> Sent: Thursday, January 9, 2014 10:40:28 AM
>> Subject: Re: [Users] oVirt 3.4.0 release schedule updated
>>
>>
>>
>> ----- Original Message -----
>>> From: "Sandro Bonazzola" <sbonazzo at redhat.com>
>>> To: "engine-devel" <engine-devel at ovirt.org>, "VDSM Project Development"
>>> <vdsm-devel at lists.fedorahosted.org>,
>>> "vdsm-devel" <vdsm-devel at fedorahosted.org>, "arch" <arch at ovirt.org>,
>>> Users at ovirt.org
>>> Sent: Wednesday, January 8, 2014 6:47:58 PM
>>> Subject: [Users] oVirt 3.4.0 release schedule updated
>>>
>>> oVirt team has updated the release schedule for 3.4.0 [1]
>>>
>>> These are tentative planning dates and may change
>>>
>>> General availability: 2014-02-24
>>> oVirt 3.4 Second Test Day: 2014-02-19
>>> RC Build: 2014-02-17
>>> oVirt 3.4 Test Day: 2014-01-27
>>
>> Please note that some guys from the TLV office could not attend to that due
>> to an Advanced Python Course taking place (27-30 JAN)
>>
>
> Hi Sandro,
> Since there's some activity also around FOSDEM, I suggest we
> will do the first test day on January 23.
>
> Please let me know if there are any objections.
>
>>> Beta release: 2014-01-20
>>> Branching / Feature freeze: 2014-01-15
>>> Alpha release: 2014-01-09
>>>
>>> more details on test days, etc to come in the next few weeks
>>>
>>> [1] http://www.ovirt.org/OVirt_3.4_release-management#Timeline
>>>
>>> --
>>> Sandro Bonazzola
>>> Better technology. Faster innovation. Powered by community collaboration.
>>> See how it works at redhat.com
>>> _______________________________________________
>>> Users mailing list
>>> Users at ovirt.org
>>> http://lists.ovirt.org/mailman/listinfo/users
>>>
>> _______________________________________________
>> Users mailing list
>> Users at ovirt.org
>> http://lists.ovirt.org/mailman/listinfo/users
>>
--
Sandro Bonazzola
Better technology. Faster innovation. Powered by community collaboration.
See how it works at redhat.com
-------------- next part --------------
A non-text attachment was scrubbed...
Name: ovirt-roadmap.ics
Type: text/calendar
Size: 2616 bytes
Desc: not available
URL: <http://lists.ovirt.org/pipermail/arch/attachments/20140109/e7d27f25/attachment.ics>