[ovirt-users] Pending events in the Tasks tab
nicolas at devels.es
nicolas at devels.es
Wed Feb 17 03:25:00 EST 2016
Hi,
We're using oVirt 3.6.2.6, and we're having some events not being
cleared from the Tasks tab. I cannot confirm this is only related to
creating VM pools, but any created VM pool remains unfinished forever in
the Tasks tab. As you may see in the screenshot, there are events that
were started in January and are still in the list. Concretely, the
unfinished step is always "Finalizing".
Has this been reported on Bugzilla?
Is there a way to clear them out even manually?
Thanks.
Nicolás
More information about the Users
mailing list