Hi, here is the proposed schedule for oVirt 3.6.0. These are tentative planning dates and may change: 2015-04-22 - Feature Submission Closed 2015-05-06 - Alpha Release 2015-05-12 - Alpha Release Test Day 2015-06-16 - Feature freeze - Stable branch 2015-07-15 - Beta Release 2015-07-20 - Beta Release Test Day 2015-08-03 - String Freeze 2015-08-19 - Release Candidate 2015-08-24 - Release Candidate Test Day 2015-09-16 - Release Release management page has been updated accordingly: http://www.ovirt.org/OVirt_3.6_Release_Management oVirt Google Calendar has been updated accordingly: ICAL: https://www.google.com/calendar/ical/ppqtk46u9cglj7l987ruo2l0f8%40group.cale... XML: https://www.google.com/calendar/feeds/ppqtk46u9cglj7l987ruo2l0f8%40group.cal... HTML: https://www.google.com/calendar/embed?src=ppqtk46u9cglj7l987ruo2l0f8%40group.calendar.google.com&ctz=UTC Thanks, -- Sandro Bonazzola Better technology. Faster innovation. Powered by community collaboration. See how it works at redhat.com

This is very far away! If counting the usual late due to blockers, we can consider that ovirt team provides actually one major release per year against two until now. We can expect a lot of 3.5.z :) Le 19/02/2015 15:27, Sandro Bonazzola a écrit :
Hi, here is the proposed schedule for oVirt 3.6.0.
These are tentative planning dates and may change:
2015-04-22 - Feature Submission Closed 2015-05-06 - Alpha Release 2015-05-12 - Alpha Release Test Day 2015-06-16 - Feature freeze - Stable branch 2015-07-15 - Beta Release 2015-07-20 - Beta Release Test Day 2015-08-03 - String Freeze 2015-08-19 - Release Candidate 2015-08-24 - Release Candidate Test Day 2015-09-16 - Release
Release management page has been updated accordingly: http://www.ovirt.org/OVirt_3.6_Release_Management
oVirt Google Calendar has been updated accordingly: ICAL: https://www.google.com/calendar/ical/ppqtk46u9cglj7l987ruo2l0f8%40group.cale... XML: https://www.google.com/calendar/feeds/ppqtk46u9cglj7l987ruo2l0f8%40group.cal... HTML: https://www.google.com/calendar/embed?src=ppqtk46u9cglj7l987ruo2l0f8%40group.calendar.google.com&ctz=UTC
Thanks,

Il 19/02/2015 15:37, Nathanaël Blanchet ha scritto:
This is very far away! If counting the usual late due to blockers, we can consider that ovirt team provides actually one major release per year against two until now. We can expect a lot of 3.5.z :)
Yep, lot of 3.5.z :-)
Le 19/02/2015 15:27, Sandro Bonazzola a écrit :
Hi, here is the proposed schedule for oVirt 3.6.0.
These are tentative planning dates and may change:
2015-04-22 - Feature Submission Closed 2015-05-06 - Alpha Release 2015-05-12 - Alpha Release Test Day 2015-06-16 - Feature freeze - Stable branch 2015-07-15 - Beta Release 2015-07-20 - Beta Release Test Day 2015-08-03 - String Freeze 2015-08-19 - Release Candidate 2015-08-24 - Release Candidate Test Day 2015-09-16 - Release
Release management page has been updated accordingly: http://www.ovirt.org/OVirt_3.6_Release_Management
oVirt Google Calendar has been updated accordingly: ICAL: https://www.google.com/calendar/ical/ppqtk46u9cglj7l987ruo2l0f8%40group.cale... XML: https://www.google.com/calendar/feeds/ppqtk46u9cglj7l987ruo2l0f8%40group.cal... HTML: https://www.google.com/calendar/embed?src=ppqtk46u9cglj7l987ruo2l0f8%40group.calendar.google.com&ctz=UTC
Thanks,
_______________________________________________ Users mailing list Users@ovirt.org http://lists.ovirt.org/mailman/listinfo/users
-- Sandro Bonazzola Better technology. Faster innovation. Powered by community collaboration. See how it works at redhat.com
participants (2)
-
Nathanaël Blanchet
-
Sandro Bonazzola