Release Schedule
Livnat Peer
lpeer at redhat.com
Wed Oct 9 16:47:28 UTC 2013
On 10/09/2013 06:01 PM, Itamar Heim wrote:
> Our current release schedule is "~6 months".
> we've found this is a long cycle, causing:
> - time to deliver is long - no reason we can't stabilize chunks in
> shorter cycles.
> - the stabilization cycle is very long.
>
> I've proposed we trim down the schedule to 3-4 months for now, to reduce
> time to delivery and shorten the stabilization cycle.
>
+1
I am all for it, I think shorter release cycles would also help us to
deliver fixes which are not critical but are still annoying faster to
oVirt users.
> Thanks,
> Itamar
> _______________________________________________
> Board mailing list
> Board at ovirt.org
> http://lists.ovirt.org/mailman/listinfo/board
More information about the Board
mailing list