[ovirt-users] oVirt 3.6.0 release schedule update
Sandro Bonazzola
sbonazzo at redhat.com
Thu Feb 19 14:27:08 UTC 2015
Hi,
here is the proposed schedule for oVirt 3.6.0.
These are tentative planning dates and may change:
2015-04-22 - Feature Submission Closed
2015-05-06 - Alpha Release
2015-05-12 - Alpha Release Test Day
2015-06-16 - Feature freeze - Stable branch
2015-07-15 - Beta Release
2015-07-20 - Beta Release Test Day
2015-08-03 - String Freeze
2015-08-19 - Release Candidate
2015-08-24 - Release Candidate Test Day
2015-09-16 - Release
Release management page has been updated accordingly:
http://www.ovirt.org/OVirt_3.6_Release_Management
oVirt Google Calendar has been updated accordingly:
ICAL: https://www.google.com/calendar/ical/ppqtk46u9cglj7l987ruo2l0f8%40group.calendar.google.com/public/basic.ics
XML: https://www.google.com/calendar/feeds/ppqtk46u9cglj7l987ruo2l0f8%40group.calendar.google.com/public/basic
HTML: https://www.google.com/calendar/embed?src=ppqtk46u9cglj7l987ruo2l0f8%40group.calendar.google.com&ctz=UTC
Thanks,
--
Sandro Bonazzola
Better technology. Faster innovation. Powered by community collaboration.
See how it works at redhat.com
More information about the Users
mailing list