Hi,
This mail is to provide the current status of CQ and allow people to review
status before and after the weekend.
Please refer to below colour map for further information on the meaning of
the colours.
*CQ-4.2*: GREEN (#1)
Last CQ job failure on 4.2 was 05-04-2019 on project ovirt-provider-ovn due
to a code regression which was caused by [1]
The issue has been found and a patch created [2] but due to the hotplug_cpu
failure, it took a long time to verify the fix before merge.
[1]
https://gerrit.ovirt.org/#/c/98723/ - Stateless dhcpv6 does not support
fixed IPs
[2]
https://gerrit.ovirt.org/#/c/99193/ - Fix bug when fixed IPs are not
provisioned
*CQ-4.3*: RED (#3)
We have been having constant failures on tests:
hotplug_cpu
add_master_storage_domain
The failures on these two are very frequent and I need to re-trigger tests
on multiple failures daily.
There is a mail thread on this and several people have joined in to help
debug the issue but I think that this issue needs more help from some of
the other teams as its been going on for the last two weeks at least.
This is also disrupting fixing actual regressions as the testing keep
failing on these two unrelated issues.
*CQ-Master:* RED (#3)
Master and 4.3 have the same issues.
Current running jobs for 4.2 [1], 4.3 [2] and master [3] can be found
here:
[1]
http://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-4.2_change-...
[2]
https://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-4.3_change...
[3]
http://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-master_chan...
Happy week!
Dafna
-------------------------------------------------------------------------------------------------------------------
COLOUR MAP
Green = job has been passing successfully
** green for more than 3 days may suggest we need a review of our test
coverage
1.
1-3 days GREEN (#1)
2.
4-7 days GREEN (#2)
3.
Over 7 days GREEN (#3)
Yellow = intermittent failures for different projects but no lasting or
current regressions
** intermittent would be a healthy project as we expect a number of
failures during the week
** I will not report any of the solved failures or regressions.
1.
Solved job failures YELLOW (#1)
2.
Solved regressions YELLOW (#2)
Red = job has been failing
** Active Failures. The colour will change based on the amount of time the
project/s has been broken. Only active regressions would be reported.
1.
1-3 days RED (#1)
2.
4-7 days RED (#2)
3.
Over 7 days RED (#3)