This mail is to provide the current status of CQ and allow people to review
status before and after the weekend.
Please refer to below colour map for further information on the meaning of
the colours.
*CQ-4.2*: GREEN (#1)
Last CQ job failure on 4.2 was 25-03-2019 on project
ovirt-ansible-hosted-engine-setup due missing polkit package.
*CQ-4.3*: RED (#1)
failures in 4.3 and master this week were caused by two issues:
1. we have had random failures on 4 different tests which we are working on
debugging with Marcin, Martin and several more people. this has been
disruptive this week but did not cause any delays as I was re-triggering
failed projects to insure they have their packages buit in tested.
Currently we suspect api issue or changes to poastgres are causing the
failures
2. we had libcgroup-tools package missing which cause failures for all
projects in initialize engine. I merged a patch to fix the issue and
provide the package.
*CQ-Master:* RED (#1)
We have had the same issues as in 4.3 this week.
Current running jobs for 4.2 [1], 4.3 [2] and master [3] can be found
here:
[1]
http://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-4.2_change-...
[2]
https://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-4.3_change...
[3]
http://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-master_chan...
Happy week!
Dafna
-------------------------------------------------------------------------------------------------------------------
COLOUR MAP
Green = job has been passing successfully
** green for more than 3 days may suggest we need a review of our test
coverage
1.
1-3 days GREEN (#1)
2.
4-7 days GREEN (#2)
3.
Over 7 days GREEN (#3)
Yellow = intermittent failures for different projects but no lasting or
current regressions
** intermittent would be a healthy project as we expect a number of
failures during the week
** I will not report any of the solved failures or regressions.
1.
Solved job failures YELLOW (#1)
2.
Solved regressions YELLOW (#2)
Red = job has been failing
** Active Failures. The colour will change based on the amount of time the
project/s has been broken. Only active regressions would be reported.
1.
1-3 days RED (#1)
2.
4-7 days RED (#2)
3.
Over 7 days RED (#3)