Hi,
This mail is to provide the current status of CQ and allow people to review
status before and after the weekend.
Please refer to below colour map for further information on the meaning of
the colours.
*CQ-4.2*: GREEN (#1)
Last CQ job failure on 4.2 was 14-03-2019 on project v2v-conversion-host
due to missing failed build artifacts which was fixed the same day.
*CQ-4.3*: RED (#1)
Last job to failed today. it had 13 changes and CQ is still bisecting the
result.
*CQ-Master:* RED (#1)
Last failure was today due to a build-artifacts failure. a message was sent
to patch owner.
Current running jobs for 4.2 [1] and master [2] can be found here:
[1]
http://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-4.2_change-...
[2]
http://jenkins.ovirt.org/view/Change%20queue%20jobs/job/ovirt-master_chan...
Happy week!
Dafna
-------------------------------------------------------------------------------------------------------------------
COLOUR MAP
Green = job has been passing successfully
** green for more than 3 days may suggest we need a review of our test
coverage
1.
1-3 days GREEN (#1)
2.
4-7 days GREEN (#2)
3.
Over 7 days GREEN (#3)
Yellow = intermittent failures for different projects but no lasting or
current regressions
** intermittent would be a healthy project as we expect a number of
failures during the week
** I will not report any of the solved failures or regressions.
1.
Solved job failures YELLOW (#1)
2.
Solved regressions YELLOW (#2)
Red = job has been failing
** Active Failures. The colour will change based on the amount of time the
project/s has been broken. Only active regressions would be reported.
1.
1-3 days RED (#1)
2.
4-7 days RED (#2)
3.
Over 7 days RED (#3)