Hello Gianluca,
This is not the right flow. If you would like to have any other network in
your cluster as the management network, then you need to create it as the
management network of the cluster and then add hosts to the cluster, then
the new network which was defined as the management network of the cluster
will be the management network of the host/s in the cluster.
The correct flow will be :
1) Create new network for example - 'net1-mgmt'
2) Give 'net1-mgmt' a management role via manage networks, it can be done
via networks>clusters flow or via Cluster>logical networks flow(note that
management network must be required and attached)
3) Create cluster and choose 'net1-mgmt' as the management network of the
cluster
3) Add/install the host in the cluster
See also -
https://www.ovirt.org/develop/release-management/features/network/managem...
It's a network feature since 3.6
Cheers)
On Wed, Sep 27, 2017 at 12:27 PM, Gianluca Cecchi <gianluca.cecchi(a)gmail.com
wrote:
Hello,
I notice that in a cluster I can create a new network and then select it
as the Management network, but at the same time the default "ovirtmgmt"
logical network in "Manage Networks" is always checked as both as
"Assign"
and "Required" and also grayed so that I cannot change anything of it...
and any host in this cluster must have ovirtmgmt even if it doesn't use it
at all..
Is there any RFE to change this model?
So for example to be able to change its name or delete it after we have
defined a new network as management one.
It seems something similar to the concept of the"Default" DC that now we
can finally rename and /or delete
Gianluca
_______________________________________________
Users mailing list
Users(a)ovirt.org
http://lists.ovirt.org/mailman/listinfo/users
--
Michael Burman
Quality engineer - rhv network - redhat israel
Red Hat
<
https://www.redhat.com>
mburman(a)redhat.com M: 0545355725 IM: mburman
<
https://red.ht/sig>