i didn't see any date for stable branch creation, or it's called by a different
name?
also, worth maybe doing an internal discussion on ovirt vs rhev 3.6 release, in terms of
milestones, qe verification on upstream, etc...
e.
----- Original Message -----
From: "Sandro Bonazzola" <sbonazzo(a)redhat.com>
To: devel(a)ovirt.org
Cc: "Juan Hernandez" <jhernand(a)redhat.com>, "Barak Azulay"
<bazulay(a)redhat.com>, "Yaniv Dary" <ydary(a)redhat.com>,
"Einav Cohen" <ecohen(a)redhat.com>, "Dan Kenigsberg"
<danken(a)redhat.com>, "Fabian Deutsch" <fabiand(a)redhat.com>,
"Yaniv Bronheim" <ybronhei(a)redhat.com>, "Martin Sivak"
<msivak(a)redhat.com>, "Tomas Jelinek" <tjelinek(a)redhat.com>,
"Adam Litke" <alitke(a)redhat.com>, "Itamar Heim"
<iheim(a)redhat.com>, "Doron Fediuck" <dfediuck(a)redhat.com>,
"Eyal
Edri" <eedri(a)redhat.com>, "David Caro" <dcaroest(a)redhat.com>,
"Oved Ourfalli" <ovedo(a)redhat.com>, "Lior Vernia"
<lvernia(a)redhat.com>, "Allon Mureinik" <amureini(a)redhat.com>,
"Michal Skrivanek" <mskrivan(a)redhat.com>, "Gil Klein"
<gklein(a)redhat.com>
Sent: Tuesday, October 28, 2014 12:02:00 PM
Subject: Reminder: [ovirt-users] [QE][ACTION REQUIRED] oVirt 3.6.0 status - release
criteria
Hi,
since I don't see activity on this, just a gentle reminder that we should
close release criteria discussion for 2014-11-12.
Is everybody happy just with what was proposed
here:
http://lists.ovirt.org/pipermail/devel/2014-September/008695.html
and here:
http://lists.ovirt.org/pipermail/users/2014-October/028451.html
?
Il 22/10/2014 09:21, Sandro Bonazzola ha scritto:
> Hi,
> according to oVirt Release Process [1], a week after the n-1 release is
> out, a release criteria for the new release should be discussed.
>
> Release criteria will include MUST items and SHOULD items (held in wiki)
> MUST items will DELAY the release in any case.
> SHOULD items will include less critical flows and new features.
> SHOULD items will be handled as "best-effort" by component owners
> Component owners (e.g. Node, engine-core, vdsm) must ACK the criteria
> suggested.
> Release criteria discussions shouldn't take more then 2 weeks
> Progress on MUST items should be review every month, during the weekly
> meeting
>
> This means that starting today, we should define release criteria for
> November 12th.
> A couple of email have been already posted about this:
>
> * LINK:
http://lists.ovirt.org/pipermail/devel/2014-August/008533.html
> * LINK:
http://lists.ovirt.org/pipermail/devel/2014-September/008695.html
>
> as starting point for the discussion.
>
> Release management for 3.6.0 has been created [2]
> The key milestones for this release must be scheduled:
>
> Key Milestones
> Release criteria discussion start: 2014-10-22
> Release criteria ready: 2014-11-12
> Feature freeze: 60 Days before release
> First Test Day: 45 days before release
> Release Candidate: 30 days before release
> Release: 6 months after oVirt 3.5.0 release
>
> A tracker bug for 3.6.0 has been created [3] and currently show no
> blockers.
>
> There are 384 bugs [4] targeted to 3.6.0.
> Excluding node and documentation bugs we have 364 bugs [5] targeted to
> 3.6.0.
>
> [1]
http://www.ovirt.org/Release_process
> [2]
http://www.ovirt.org/OVirt_3.6_Release_Management
> [3]
https://bugzilla.redhat.com/show_bug.cgi?id=1155425
> [4]
http://goo.gl/zwkF3r
> [5]
http://goo.gl/ZbUiMc
>
--
Sandro Bonazzola